Another milestone for Temburong Bridge Project

THE construction of the Temburong Bridge Project marked another important milestone, where the 578th and last box girder for CC2-Marine Viaduct Package was installed yesterday.

Minister of Development Dato Seri Setia Awang Haji Suhaimi bin Haji Gafar, Deputy Minister of Development Haji Marzuke bin Haji Mohsin and Ambassador of Republic of Korea to Brunei Darussalam Yoon Hyun-bong witnessed the installation.

The construction of the CC2-Marine Viaducts Package is carried out by the DaelimSwee Joint Venture company. The construction commenced on February 25, 2015, taking up 48 months for its completion.

The installation of the final box girder completed the construction of the 13.35-kilometre Marine Bridge, which is the biggest part of the Temburong Bridge Project. It also marked that the Marine Bridge is now linked to the CC4 Package which is the construction of part of the bridge in the Temburong District.

Minister of Development Dato Seri Setia Awang Haji Suhaimi bin Haji Gafar and Ambassador of Republic of Korea to Brunei Darussalam Yoon Hyun-bong in a group photo. – MINISTRY OF DEVELOPMENT